Administrative procedures hinder flood control projects

Despite great efforts taken by Ho Chi Minh City’s authorities to fight flooding, many flood-control projects have been delayed by administrative procedures.

Residents of certain areas in the city have suffered from floods for decades, especially in the rainy season when roads and houses are flooded at high tide.

One of the city’s seven key economic development programmes in the 2016-2020 period, the flood combating programme has called for investment from the private sector

Investments were mobilised to build a huge pumping system on Nguyen Huu Canh street in Binh Thanh district and to combat high tides caused by climate change.

With an investment of nearly VND10 trillion (US$427.6 million), construction of the first stage of the project to combat flooding caused by high tides began in June 2016.

The project covered 570 sq.km area with a population of 6.5 million on the right bank of the Sai Gon River and the downtown area of the city. Construction was scheduled to last 36 months and end in June next year.

The investors of the project later said construction would be completed in 24 months, and said if the site had been transferred to the investors in due time, site clearance would have been completed by April.

However, on April 27 this year, the investor said construction had been suspended because the city authority had not “signed papers for the bank to provide funds” for the project. Construction was also hindered due to delays in site clearance.

The project, invested in by the Quang Trung Group, includes the huge pump on Nguyen Huu Canh street in Binh Thanh district.

But the project was suspended on August 31 due to “financial problems” facing Quang Trung Group.

According to the Quang Trung Group, the pump has been operating on Nguyen Huu Canh street for two years, but the steering board of HCM City’s flood combating programme has not set rental rates for the pump.

The company’s request to advance funds for operation of the pump has not been met, according to the Quang Trung Group.

Nguyen Tang Cuong, CEO of the Quang Trung Group, said the pump had been used on 30 occasions, helping to control floods on Nguyen Huu Canh street.

The Quang Trung Group had spent several years studying the flooding situation in the area, and had operated the pump in the last two rainy seasons. But the company had no more funds to operate the pump, Cuong added.

At a press meeting last week, Nguyen Tam Tien, CEO of Trung Nam Group, the investor of the project which aims to prevent floods from high tides, said construction of the project had stopped because funding had been suspended since April 27.

The suspension has caused losses of about VND17 billion to VND20 billion per month.

Tien said 72% of the construction of the project had been completed before suspension.

VNS/VNA

Other News

Vietnam moves to adapt to rapid population ageing, expand silver economy

Vietnam moves to adapt to rapid population ageing, expand silver economy

The International Day of Older Persons 2026, themed “The Age of Longevity: Rethinking Systems for Longer Lives,” highlights the need to develop healthcare, social security, labour-market and social-service systems in response to increasing life expectancy. For Vietnam, rapid population ageing is not only a demographic issue but also a development challenge.

Vietnamese, Lao localities bolster Front cooperation

Vietnamese, Lao localities bolster Front cooperation

Both sides agreed to keep educating officials, Party members, youth union groups and the broader public, especially young people in both provinces, on the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between Vietnam and Laos.

Urgent rescue launched for Merchant Mariner off Quang Ngai

Urgent rescue launched for Merchant Mariner off Quang Ngai

The captain discovered water entering ballast tanks No. 4, 5 and 6 on the port side, causing the vessel to list slightly. Initial assessments indicated that the vessel may have struck an underwater rock formation while underway.

Publishing copyright caught in crossfire of piracy, AI

Publishing copyright caught in crossfire of piracy, AI

Publishing copyright is entering an entirely new phase. As AI becomes increasingly capable of generating text, summarising books, mimicking writing styles and producing content at enormous speed, ensuring copyright protection is becoming more difficult.

Heavy rains cause widespread damage in Phu Tho, Thanh Hoa

Heavy rains cause widespread damage in Phu Tho, Thanh Hoa

Prolonged heavy rains from September 13–17 have caused flooding and landslides, damaging homes, crops, roads and infrastructure in Phu Tho and Thanh Hoa provinces, with local authorities mobilising forces for emergency response.

Quang Ninh police bust 38.4 million USD transnational cybercrime ring

Quang Ninh police bust 38.4 million USD transnational cybercrime ring

Quang Ninh city's Public Security Department warned individuals, agencies and businesses not to publicly disclose or provide personal information or bank account details on social media, and urged organisations and businesses to strictly comply with regulations on protecting customers’ personal data.

Search area expanded to recover more martyrs' remains in Quang Tri

Search area expanded to recover more martyrs' remains in Quang Tri

The continued recovery of martyrs’ remains provides valuable information and further evidence of those who fought and sacrificed their lives for national independence and freedom. It also encourages search teams to persist in locating fallen soldiers still lying on former battlefields, contributing to the effective implementation of the 500-day campaign and reflecting Vietnam’s long-standing tradition of gratitude.

Vietnam to screen students nationwide for five health risks from 2028

Vietnam to screen students nationwide for five health risks from 2028

Vietnam will launch nationwide screening for five groups of school-related diseases and health conditions among students from preschool through high school from 2028, including overweight and obesity, refractive errors, spinal curvature, oral diseases and mental health disorders.