Hanoi accelerates seven Red River bridge projects, many exceed 70% completion

According to the municipal Transport Construction Investment Project Management Board, the city is simultaneously implementing seven projects, namely Tu Lien, Ngoc Hoi, Tran Hung Dao, Thuong Cat, Van Phuc, Hong Ha and Me So bridges. Construction is being carried out on multiple fronts, focusing on bored piles, pile caps, piers and superstructure works.

Hanoi accelerates seven Red River bridge projects, many exceed 70% completion -0
Construction site of Tu Lien bridge, along Nghi Tam Street (Photo: VNA)

As of early May, a series of bridge projects spanning the Red River in Hanoi are being fast-tracked, with several recording significant progress. However, site clearance, relocation of technical infrastructure and construction conditions remain critical factors affecting overall timelines.

According to the municipal Transport Construction Investment Project Management Board, the city is simultaneously implementing seven projects, namely Tu Lien, Ngoc Hoi, Tran Hung Dao, Thuong Cat, Van Phuc, Hong Ha and Me So bridges. Construction is being carried out on multiple fronts, focusing on bored piles, pile caps, piers and superstructure works.

Among them, component project 2 of Tu Lien Bridge has handed over over 80% of the required site area, with key foundation works largely completed and superstructure construction underway.

Ngoc Hoi Bridge has also made notable progress, completing most main pier piles and advancing substructure and beam casting works.

Tran Hung Dao Bridge is being executed in parallel across its main and approach sections after receiving over 77% of the site area, with nearly all households agreeing to handover. Thuong Cat Bridge has maintained stable progress, while Van Phuc Bridge, benefiting from completed site clearance, has accelerated construction across major components.

Within the Ring Road 4 project cluster, Hong Ha and Me So bridges are also gaining momentum, with substantial completion of bored piles, piers and beam installation. City leaders have maintained close oversight of progress.

During site inspections in mid-April, officials stressed the need to resolve bottlenecks, particularly land clearance, while requiring contractors to mobilise maximum resources and proceed with construction wherever land is available. The target is to put key bridges such as Tu Lien and Tran Hung Dao into operation in the second quarter of 2027.

For the Me So bridge, municipal leaders instructed relevant units to closely manage site clearance and construction support infrastructure.

For the Ngoc Hoi bridge, the requirement is to thoroughly review bottlenecks related to land and technical infrastructure and promptly adopting solutions to address any delays.

At the same time, authorities emphasised that progress must go hand in hand with quality, safety and durability.

Hung Yen province must complete site clearance for the remaining agricultural land by June 30 and residential land by July 15. Meanwhile, Hanoi’s Department of Agriculture and Environment is tasked with coordinating the clearance of pressure relief wells within the right-bank Red River dyke corridor by May 10.

Despite steady construction progress, recent reports indicate that additional site handover remains limited in some key areas, continuing to pose a major bottleneck. The city has urged local authorities to expedite clearance of remaining land and complete relocation of underground and overhead infrastructure in line with set deadlines.

Under pressing timeline requirements, the city has urged communes and wards involved in the Tu Lien, Ngoc Hoi, Tran Hung Dao and Thuong Cat bridge projects to expedite clearance of the remaining land in line with previous directions of the municipal Party Committee, while completing the relocation of underground and overhead infrastructure by May 15.

The simultaneous development of seven Red River bridges is expected to mark a major step forward in Hanoi’s transport infrastructure, enhancing regional connectivity, easing pressure on existing crossings and opening up new urban development space along both riverbanks.

VNA

Other News

Vietnam steps up implementation of ethnic affairs strategy through 2030

Vietnam steps up implementation of ethnic affairs strategy through 2030

To accelerate the implementation of the the Ethnic Affairs Strategy by 2030, with a vision toward 2045, the Prime Minister requested ministries, agencies and local authorities to continue thoroughly carrying out the Party and State’s policies on ethnic affairs, enhancing the effectiveness of State management and strengthening oversight of policy implementation.

Security preparations reviewed for APEC 2027 in Phu Quoc

Security preparations reviewed for APEC 2027 in Phu Quoc

The team examined the APEC 2027 Convention Centre, where main conference activities are scheduled; Sun Serenia Hospital, designated to provide healthcare and emergency medical services for delegates; provincial road DT.975, which connects Phu Quoc International Airport to the convention centre; and the area surrounding Phu Quoc International Airport.

Dien Bien battlefield legacy powers tourism revival

Dien Bien battlefield legacy powers tourism revival

Seventy-two years after the Dien Bien Phu Victory, its legacy still reverberates. The unity, self-reliance, and resilience forged in that historic triumph remain a powerful internal engine, now propelling Dien Bien toward fast and sustainable development.

Hanoi accelerates shift to green buses, targets 100% by 2030

Hanoi accelerates shift to green buses, targets 100% by 2030

In the 2027–2030 period, the city will accelerate the transition towards the complete phase-out of fossil fuel-powered buses. The share of electric and green energy-fueled buses is projected to reach 79–89% by 2029 and 100% by 2030.

36 fishermen safely rescued after boat breaks down near Truong Sa

36 fishermen safely rescued after boat breaks down near Truong Sa

At 8:00 the same day, KN475 began towing the disabled fishing boat toward Da Tay A island. The towing operation was carried out safely, and by 18:30 both the vessel and its crew had arrived at the island without incident, where repairs and additional support procedures were arranged.

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Held in response to the launch of the Vietnamese Language Day among overseas Vietnamese communities, the event aimed to enhance the quality of Vietnamese language teaching and learning in Laos while contributing to the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between the two countries.

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Held in response to the launch of the Vietnamese Language Day among overseas Vietnamese communities, the event aimed to enhance the quality of Vietnamese language teaching and learning in Laos while contributing to the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between the two countries.

Hanoi launches 10 electric bus routes from April 1

Hanoi launches 10 electric bus routes from April 1

By the end of April, the number of buses using electricity and other green energy sources in the city is expected to reach 822, including 683 electric buses and 139 compressed natural gas (CNG) buses, representing 42.1% of the total number of vehicles.

Publishing sector accelerates digital ecosystem development

Publishing sector accelerates digital ecosystem development

According to the Department of Publishing, Printing and Distribution, the country currently has 52 publishing houses. In 2025, the industry produced more than 51,000 publications, with around 543 million copies and online accesses, generating total revenue of over 4.1 trillion VND (nearly 155.64 million USD).