HCM City seeks more metro line funding

HCM City’s metro lines are facing various issues with procedures, disbursement, and cost overrun.

On-going construction of Metro Line 1 in HCM City
On-going construction of Metro Line 1 in HCM City

The HCM City Urban Railway Management Board recently asked the city people's committee to give VND1trn (USD44m) in advance to pay contractors working on the Metro Line 1 this year. This is the fourth time the city has advanced funds because the government has been too slow with disbursement. The city had to pay VND600bn in late 2016 and in 2017, the city paid VND500bn and then VND1.2trn in advance.

According to the Ministry of Planning and Investment, the National Assembly had yet to approve the final cost and the re-lending ratio of ODA from Japan hasn't been specified. 

Metro Line 1 was approved by the city in 2007 with an investment of VND17.40trn (USD766.4m). Approval by the National Assembly was not needed at that time.

A member of the HCM City Urban Railway Management Board said at first the city hired a local consultancy company to do the pre-feasibility study report. This company wanted to make cheap metro lines but they were not up to Japan International Co-operation Agency's standards. JICA then hired two companies from Singapore to estimate the cost for higher standard metro lines and the investment cost increased to VND47.30trn (USD2.08bn).

HCM City People's Committee said the currency exchange, minimum wage increase, and inflation also played important parts in the cost-overrun.

However, in 2011, the metro line became a key national project with huge investment cost so it needs approval from the National Assembly. After the prime minister allowed HCM City to continue, they signed three loans agreement worth VND31.20trn (USD1.37bn), of which VND12trn has been disbursed. 50% of the project is completed but disbursement was stopped and the city now lacks fund to pay contractors.

HCM City Chairman Nguyen Thanh Phong has sent a letter to the National Assembly Chairwoman Nguyen Thi Kim Ngan and Prime Minister Nguyen Xuan Phuc, outlining the consequences if Metro Line 1 is not completed in time.

In addition to the relationship with Japan being affected, it may impact on future ODA projects. 

"Disputes, lawsuits and wasted capital will occur as we still have to pay commitment fees and arrangement fees for loan agreements," he said.

He asked all agencies to help speed up the NA's approval in coming meetings. The Ministry of Planning and Investment was asked to continue to disburse the funding.

Metro Line 2 also experienced a similar cost-overrun from USD1.37bn to USD2.17bn after being reviewed by foreign consultants.

Dtinews/Tien Phong

Other News

Vietnam moves to adapt to rapid population ageing, expand silver economy

Vietnam moves to adapt to rapid population ageing, expand silver economy

The International Day of Older Persons 2026, themed “The Age of Longevity: Rethinking Systems for Longer Lives,” highlights the need to develop healthcare, social security, labour-market and social-service systems in response to increasing life expectancy. For Vietnam, rapid population ageing is not only a demographic issue but also a development challenge.

Vietnamese, Lao localities bolster Front cooperation

Vietnamese, Lao localities bolster Front cooperation

Both sides agreed to keep educating officials, Party members, youth union groups and the broader public, especially young people in both provinces, on the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between Vietnam and Laos.

Urgent rescue launched for Merchant Mariner off Quang Ngai

Urgent rescue launched for Merchant Mariner off Quang Ngai

The captain discovered water entering ballast tanks No. 4, 5 and 6 on the port side, causing the vessel to list slightly. Initial assessments indicated that the vessel may have struck an underwater rock formation while underway.

Publishing copyright caught in crossfire of piracy, AI

Publishing copyright caught in crossfire of piracy, AI

Publishing copyright is entering an entirely new phase. As AI becomes increasingly capable of generating text, summarising books, mimicking writing styles and producing content at enormous speed, ensuring copyright protection is becoming more difficult.

Heavy rains cause widespread damage in Phu Tho, Thanh Hoa

Heavy rains cause widespread damage in Phu Tho, Thanh Hoa

Prolonged heavy rains from September 13–17 have caused flooding and landslides, damaging homes, crops, roads and infrastructure in Phu Tho and Thanh Hoa provinces, with local authorities mobilising forces for emergency response.

Quang Ninh police bust 38.4 million USD transnational cybercrime ring

Quang Ninh police bust 38.4 million USD transnational cybercrime ring

Quang Ninh city's Public Security Department warned individuals, agencies and businesses not to publicly disclose or provide personal information or bank account details on social media, and urged organisations and businesses to strictly comply with regulations on protecting customers’ personal data.

Search area expanded to recover more martyrs' remains in Quang Tri

Search area expanded to recover more martyrs' remains in Quang Tri

The continued recovery of martyrs’ remains provides valuable information and further evidence of those who fought and sacrificed their lives for national independence and freedom. It also encourages search teams to persist in locating fallen soldiers still lying on former battlefields, contributing to the effective implementation of the 500-day campaign and reflecting Vietnam’s long-standing tradition of gratitude.

Vietnam to screen students nationwide for five health risks from 2028

Vietnam to screen students nationwide for five health risks from 2028

Vietnam will launch nationwide screening for five groups of school-related diseases and health conditions among students from preschool through high school from 2028, including overweight and obesity, refractive errors, spinal curvature, oral diseases and mental health disorders.