HCM City seeks more metro line funding

HCM City’s metro lines are facing various issues with procedures, disbursement, and cost overrun.

On-going construction of Metro Line 1 in HCM City
On-going construction of Metro Line 1 in HCM City

The HCM City Urban Railway Management Board recently asked the city people's committee to give VND1trn (USD44m) in advance to pay contractors working on the Metro Line 1 this year. This is the fourth time the city has advanced funds because the government has been too slow with disbursement. The city had to pay VND600bn in late 2016 and in 2017, the city paid VND500bn and then VND1.2trn in advance.

According to the Ministry of Planning and Investment, the National Assembly had yet to approve the final cost and the re-lending ratio of ODA from Japan hasn't been specified. 

Metro Line 1 was approved by the city in 2007 with an investment of VND17.40trn (USD766.4m). Approval by the National Assembly was not needed at that time.

A member of the HCM City Urban Railway Management Board said at first the city hired a local consultancy company to do the pre-feasibility study report. This company wanted to make cheap metro lines but they were not up to Japan International Co-operation Agency's standards. JICA then hired two companies from Singapore to estimate the cost for higher standard metro lines and the investment cost increased to VND47.30trn (USD2.08bn).

HCM City People's Committee said the currency exchange, minimum wage increase, and inflation also played important parts in the cost-overrun.

However, in 2011, the metro line became a key national project with huge investment cost so it needs approval from the National Assembly. After the prime minister allowed HCM City to continue, they signed three loans agreement worth VND31.20trn (USD1.37bn), of which VND12trn has been disbursed. 50% of the project is completed but disbursement was stopped and the city now lacks fund to pay contractors.

HCM City Chairman Nguyen Thanh Phong has sent a letter to the National Assembly Chairwoman Nguyen Thi Kim Ngan and Prime Minister Nguyen Xuan Phuc, outlining the consequences if Metro Line 1 is not completed in time.

In addition to the relationship with Japan being affected, it may impact on future ODA projects. 

"Disputes, lawsuits and wasted capital will occur as we still have to pay commitment fees and arrangement fees for loan agreements," he said.

He asked all agencies to help speed up the NA's approval in coming meetings. The Ministry of Planning and Investment was asked to continue to disburse the funding.

Metro Line 2 also experienced a similar cost-overrun from USD1.37bn to USD2.17bn after being reviewed by foreign consultants.

Dtinews/Tien Phong

Other News

Vietnam steps up implementation of ethnic affairs strategy through 2030

Vietnam steps up implementation of ethnic affairs strategy through 2030

To accelerate the implementation of the the Ethnic Affairs Strategy by 2030, with a vision toward 2045, the Prime Minister requested ministries, agencies and local authorities to continue thoroughly carrying out the Party and State’s policies on ethnic affairs, enhancing the effectiveness of State management and strengthening oversight of policy implementation.

Security preparations reviewed for APEC 2027 in Phu Quoc

Security preparations reviewed for APEC 2027 in Phu Quoc

The team examined the APEC 2027 Convention Centre, where main conference activities are scheduled; Sun Serenia Hospital, designated to provide healthcare and emergency medical services for delegates; provincial road DT.975, which connects Phu Quoc International Airport to the convention centre; and the area surrounding Phu Quoc International Airport.

Hanoi accelerates seven Red River bridge projects, many exceed 70% completion

Hanoi accelerates seven Red River bridge projects, many exceed 70% completion

According to the municipal Transport Construction Investment Project Management Board, the city is simultaneously implementing seven projects, namely Tu Lien, Ngoc Hoi, Tran Hung Dao, Thuong Cat, Van Phuc, Hong Ha and Me So bridges. Construction is being carried out on multiple fronts, focusing on bored piles, pile caps, piers and superstructure works.

Dien Bien battlefield legacy powers tourism revival

Dien Bien battlefield legacy powers tourism revival

Seventy-two years after the Dien Bien Phu Victory, its legacy still reverberates. The unity, self-reliance, and resilience forged in that historic triumph remain a powerful internal engine, now propelling Dien Bien toward fast and sustainable development.

Hanoi accelerates shift to green buses, targets 100% by 2030

Hanoi accelerates shift to green buses, targets 100% by 2030

In the 2027–2030 period, the city will accelerate the transition towards the complete phase-out of fossil fuel-powered buses. The share of electric and green energy-fueled buses is projected to reach 79–89% by 2029 and 100% by 2030.

36 fishermen safely rescued after boat breaks down near Truong Sa

36 fishermen safely rescued after boat breaks down near Truong Sa

At 8:00 the same day, KN475 began towing the disabled fishing boat toward Da Tay A island. The towing operation was carried out safely, and by 18:30 both the vessel and its crew had arrived at the island without incident, where repairs and additional support procedures were arranged.

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Held in response to the launch of the Vietnamese Language Day among overseas Vietnamese communities, the event aimed to enhance the quality of Vietnamese language teaching and learning in Laos while contributing to the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between the two countries.

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Held in response to the launch of the Vietnamese Language Day among overseas Vietnamese communities, the event aimed to enhance the quality of Vietnamese language teaching and learning in Laos while contributing to the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between the two countries.

Hanoi launches 10 electric bus routes from April 1

Hanoi launches 10 electric bus routes from April 1

By the end of April, the number of buses using electricity and other green energy sources in the city is expected to reach 822, including 683 electric buses and 139 compressed natural gas (CNG) buses, representing 42.1% of the total number of vehicles.