Chinese contractor asks to further delay Hanoi's first sky train

The main contractor of Hanoi's first elevated railway line running from Cat Linh to Ha Dong, to the north of Hanoi, has suggested pushing back the project's deadlines to late 2018, according to the Transport Ministry.

Work on the Cat Linh-Ha Dong elevated railway, which will run over more than 13 kilometers (8 miles), started in October 2011 and was originally scheduled for completion in 2013. Photo by VnExpress/Ngoc Thanh
Work on the Cat Linh-Ha Dong elevated railway, which will run over more than 13 kilometers (8 miles), started in October 2011 and was originally scheduled for completion in 2013. Photo by VnExpress/Ngoc Thanh

Under the new schedule, the project would have test runs in early September 2018, and would be put into operation in November 2018. 

This would result in an 11-month delay compared to the previously proposed schedule, which would have seen test runs in October this year and a fully operational elevated railway by mid-2018.

"This is only the Chinese contractor's estimation, not an official schedule," said Nguyen Ngoc Dong, vice minister of transport. "The Transport Ministry has tasked the project's management board with reviewing its progress, and would report to the prime minister in January 2018."

The main contractor, the state-owned China Railway Sixth Group Co., claimed delayed disbursment of $250 million in official development assistance (ODA) from China is still the cause of the delay.

The main contractor still owes Vietnamese contractors over VND600 billion (US$26.5 million), despite already taking over US$65 million from its own working capital to pay them.

In October, the project's general manager Tang Hong said he had reported to the Chinese embassy to urge the disbursement as well as worked with the Transport Ministry to speed up the project.

According to Dong, Vietnam has resolved all disbursement issues on its side but the necessary procedures on China's side have yet to be completed.

Currently 95% of the project's construction work has been completed, while 60 percent of imported equipment has arrived in Vietnam and 40% of equipment has been installed. The contractors are expected to install the project's signal and electronic systems, as well as finish construction of railway stations in the coming months.

Work on the Cat Linh-Ha Dong elevated railway, which will run over more than 13 kilometers (8 miles), started in October 2011 and was originally scheduled for completion in 2013. But several hurdles, including issues with the Chinese contractor, have been stalling the project for years.

The original cost estimate of US$552.86 million has also ballooned to more than US$868 million, including US$670 million in loans from China.

VnExpress

Other News

Vietnamese students shine at AIMO 2026 international finals

Vietnamese students shine at AIMO 2026 international finals

The Vietnamese team won one Champion title, four First Runner-up awards, three Second Runner-up awards, 42 gold medals, 83 silver medals, 70 bronze medals and two consolation prizes at the 2026 International Finals of the Asia International Mathematical Olympiad Open Contest (AIMO) held in Hanoi on August 2-5.

Politburo's Resolution 57-NQ/TW powers new growth momentum

Politburo's Resolution 57-NQ/TW powers new growth momentum

NSO Director Nguyen Thi Huong said alongside foreign investment and the green economy, science – technology, innovation, the digital economy and digital transformation are the new drivers that can can pack a serious second-half punch.

Vietnam’s poverty reduction miracle: A journey for the people

Vietnam’s poverty reduction miracle: A journey for the people

From a country where more than 50% of the population lived below the poverty line in the early 1990s, Vietnam has reduced its poverty rate to just 2.95% today. This achievement reflects not only the effectiveness of socio-economic development policies, but also Vietnam’s ability to translate growth into tangible opportunities for its people, steadily realizing inclusive development and ensuring that no one is left behind.

Can Tho boosts Vietnamese language support for ethnic minority children

Can Tho boosts Vietnamese language support for ethnic minority children

Backed by more than 4.2 billion VND (161,000 USD) from the State budget, the programme aims to strengthen children's Vietnamese communication skills before they begin primary school, helping them integrate more smoothly into the classroom and improve learning outcomes from the outset.

Powering growth: Ensuring reliable energy supply to keep investment flowing

Powering growth: Ensuring reliable energy supply to keep investment flowing

Across Ha Tinh and Nghe An, maintenance teams conduct inspections day and night, using thermal cameras and drones to detect potential faults without interrupting electricity supply. Their work helps ensure stable power supply for businesses as the region accelerates development in line with the Government's economic growth targets.

One Vietnamese worker killed in Japan earthquake

One Vietnamese worker killed in Japan earthquake

The Embassy of Vietnam in Japan and its labour management board are actively implementing citizen protection measures and maintaining close contact with relevant organisations and companies employing Vietnamese workers in the affected areas to monitor the situation.

Hanoi to support low-income residents in replacing high-emission motorbikes

Hanoi to support low-income residents in replacing high-emission motorbikes

A key task is to formulate a support scheme for low-income residents to replace ageing motorcycles and mopeds that fail to meet emission standards and pose a high risk of pollution. It will also propose funding to provide free first-time emission testing for motorcycles and mopeds across the city.

UNESCO endorses vision for restoring Thang Long Imperial Citadel's central axis

UNESCO endorses vision for restoring Thang Long Imperial Citadel's central axis

The committee commended Vietnam for fulfilling the commitments it has made since the citadel was inscribed on the UNESCO World Heritage List in 2010, as well as for implementing recommendations from the committee and its advisory bodies. It also praised the country's efforts to preserve the site's cultural, historical and social values, transforming the imperial citadel into a space for public engagement, cultural exchange and historical education. The committee further welcomed the long-term vision as an important basis for the proposed restoration of Kinh Thien Palace in line with the approved conservation strategy.

Border guards seize 15,200 drug pills, heroin in major trafficking bust

Border guards seize 15,200 drug pills, heroin in major trafficking bust

At about 10:15 pm on July 20, officers from the Operations Division of the Nghe An Border Guard Command and the Nam Can International Border Gate Border Guard Station, in coordination with customs officers at the Nam Can International Border Gate, caught a resident of Tan Tien hamlet, Chieu Luu commune, Nghe An province, allegedly transporting narcotics in Tien Tieu hamlet, Nam Can commune.

Floods, landslides wreak havoc on northern mountainous region

Floods, landslides wreak havoc on northern mountainous region

Total economic losses were estimated at about 255 billion VND (nearly 9.7 million USD), with Lai Chau accounting for the largest share of the damage with 190 billion VND, followed by Son La with 46.04 billion VND, Lao Cai with 16.7 billion VND, and Dien Bien with 2.3 billion VND.