Measures needed for delayed thermal power projects of PVN

The Vietnam Oil and Gas Group (PVN) on July 4 provided information about the 3 major thermal power projects which are slow in progress.

The construction site of Long Phu 1 thermal power plant.
The construction site of Long Phu 1 thermal power plant. 

Thai Binh 2 thermal power plant

85% of the Thai Binh 2 thermal power plant has so far completed t. The first unit will be ready to generate electricity in June 2020, while the second one will be completed 4 months later.

The main reasons for the delay include wrongdoings of the general contractor, which are being handled by the authorities, and misuse of capital leading to increased costs, slow construction progress and legal issues.

Pham Huy Vuong, Head of the Electricity Department of PVN, suggested that the competent agencies should check and take over individual sections of the project and then continue releasing capital to the remaining ones.

He also highlighted the importance of ensuring a long-term supply of coal for the plant.

Long Phu 1 thermal power plant project (Soc Trang)

About 80% of the project has been completed. The delay has resulted from the U.S government embargo on the general contractor, Russia’s Power Machines, starting from January 26, 2018.

Power Machines on January 28, 2019, officially announced to end the EPC contract. Power Machines has in fact stopped the construction since March 15, 2019.

Song Hau 1 thermal power project

The power project costs over 43 trillion VND. It is the most promising out of the three, although the construction progress is slow compared to its schedule for 2012.

So far, about 73% of the project has been done. PVN expected to complete the construction of most items of the plant in 2019, conduct a trial run of a number of units such as demineralized water system, oil system, or electrical equipment.

PVN has asked the Government, relevant ministries and agencies to support the group and offer solutions to each project.

PVN also proposed that the Ministry of Industry and Trade and the State Capital Management Committee soon have a written report to the Prime Minister approving PVN to use its capital for the projects if the actual costs of the projects won’t exceed their adjusted total investment. At the same time, PVN will be responsible for the technical matters while producing electricity. When the supplemental funding is reimbursed to the projects, PVN will take back the advance. 

By Duy Tien

Other News

Data-driven land valuation to curb speculation: Experts

Data-driven land valuation to curb speculation: Experts

From a property-market perspective, Do Thi Thu Giang, National Director of Valuation and Advisory at Savills Vietnam, said the orientations under Resolution No. 21-NQ/TW could make the market more transparent and efficient, with property values increasingly tied to actual development and use potential.

Resolution No. 19-NQ/TW sets new growth drivers for Vietnam

Resolution No. 19-NQ/TW sets new growth drivers for Vietnam

Science and technology, innovation, digital transformation and AI must be translated into higher productivity rather than pursued as ends in themselves. At the same time, people should be placed at the centre of development, not merely viewed as a resource but as the ultimate objective of development policies.

Expo to open door for Vietnamese suppliers to enter US market

Expo to open door for Vietnamese suppliers to enter US market

US retail giant Target is seeking Vietnamese suppliers of household goods, home textiles, children’s products, personal care and beauty products, with a focus on companies capable of manufacturing and developing products that meet requirements on quality, design and supply chain management.

2026 Banking Sector Digital Transformation to open in Hanoi

2026 Banking Sector Digital Transformation to open in Hanoi

The annual event, which will be held on August 18-19, 2026, at the ICE International Exhibition Centre, 91 Tran Hung Dao Street, Hanoi, is expected to attract around 324 delegates and feature 21 booths representing credit institutions, payment intermediary service providers, and technology companies.

Vietnam – one of most attractive destinations for leading US semiconductor companies: expert

Vietnam – one of most attractive destinations for leading US semiconductor companies: expert

Vietnam has built a solid semiconductor and electronics industry before joining ITSI, attracting major US semiconductor companies. Intel Products Vietnam is one of Intel's largest assembly and testing facilities worldwide, while chip design companies such as Synopsys, Cadence, Marvell and Qualcomm have established engineering and research centres in the Southeast Asian country.

Vietnam targets higher-quality FDI under Resolution 10

Vietnam targets higher-quality FDI under Resolution 10

During the first seven months of 2026, Vietnam attracted more than 38 billion USD in registered FDI, up nearly 58% year-on-year. More importantly, the increase was driven by large-scale, high-tech projects rather than a surge in the number of new investments, signalling a significant improvement in the quality of capital inflows.

Manufacturing, engineering drive hiring growth in H1: report

Manufacturing, engineering drive hiring growth in H1: report

Manufacturing and engineering posted the strongest recruitment growth, with hiring demand surging 70% year-on-year, driven by production expansion, supply chain restructuring and sustained investment inflows in high-tech manufacturing.

Government proposes special mechanisms to unblock APEC 2027 projects in Phu Quoc

Government proposes special mechanisms to unblock APEC 2027 projects in Phu Quoc

The projects in Phu Quoc have been implemented under tight deadlines. Since May 2025, the Prime Minister has directed preparations for APEC 2027, including accelerated infrastructure development on the special zone. An Giang province and investors have subsequently launched a number of major projects involving complex technical requirements and demanding construction schedules.

Financial market reform plan targets high, sustained growth through 2045

Financial market reform plan targets high, sustained growth through 2045

The plan seeks to develop a balanced and modern financial market that is closely integrated with regional and global markets, strengthens the mobilisation and allocation of domestic and foreign capital, and enhances the market’s role as a key provider of medium- and long-term capital for the economy and as a major driver of sustained high economic growth.

An Giang aims to become leading maritime economic hub

An Giang aims to become leading maritime economic hub

Under the province's master plan for 2021–2030 with a vision to 2050, An Giang will prioritise investment in five strategic sectors: strategic infrastructure; processing industries and clean energy; trade, services, logistics and border-gate economy; high-quality tourism; and high-tech agriculture, ecological development and the circular economy.