Hanoi’s second metro line goes on trial run

PSNews - According to the Hanoi Metropolitan Railway Management Board, all eight trains of the Nhon - Hanoi Station metro line went on a test run, with the first evaluating the line’s Reliability, Availability, Maintainability and Safety (RAMS).

Hanoi’s second metro line goes on trial run -0
Photo: VNS/VNA.

The test run will be conducted in two phases, with the first phase lasting from five days to six weeks in order to evaluate the line's RAM efficiency. During the first phase, four to eight trains will run between 9 a.m. and 7 p.m.

Each train stops at a station for about 20 seconds. The entire time it takes for a train to run between two ends should be around 16 minutes, meaning a round trip takes 32 minutes.

If the efficiency recorded during the first five consecutive days of trial runs fails to reach 98 percent, the phase will be extended until the goal is achieved, to a maximum of six weeks.

The second phase of the test run will commence right after the RAMS evaluation is completed, with several scenarios being simulated, such as blackouts and fires.

The Nhon-Hanoi Railway Station metro line, the second route to be put into operation after Cat Linh-Ha Dong in the capital city, is slated to run 12.5 kilometers from Nhon in Nam Tu Liem District to the Hanoi Railway Station in the downtown area.

It will include 8.5 kilometers on elevated tracks and four kilometers underground.

Construction began in 2010 at an estimated cost of EUR783 million (US$820.3 million), which was then revised up to EUR1.1 billion ($1.15 billion) in 2014 and is mainly funded by official development assistance (ODA) from France.

It was originally expected to be finished in 2018.

However, a report by MRB showed that only 75 percent was completed, the Vietnam News Agency reported in October.

Its first train was put on a trial run in January last year.

The metro route is anticipated to help reduce 20,000 metric tons of vehicle exhaust in Hanoi each year.

By Kim Khanh

Other News

Vietnam steps up implementation of ethnic affairs strategy through 2030

Vietnam steps up implementation of ethnic affairs strategy through 2030

To accelerate the implementation of the the Ethnic Affairs Strategy by 2030, with a vision toward 2045, the Prime Minister requested ministries, agencies and local authorities to continue thoroughly carrying out the Party and State’s policies on ethnic affairs, enhancing the effectiveness of State management and strengthening oversight of policy implementation.

Security preparations reviewed for APEC 2027 in Phu Quoc

Security preparations reviewed for APEC 2027 in Phu Quoc

The team examined the APEC 2027 Convention Centre, where main conference activities are scheduled; Sun Serenia Hospital, designated to provide healthcare and emergency medical services for delegates; provincial road DT.975, which connects Phu Quoc International Airport to the convention centre; and the area surrounding Phu Quoc International Airport.

Hanoi accelerates seven Red River bridge projects, many exceed 70% completion

Hanoi accelerates seven Red River bridge projects, many exceed 70% completion

According to the municipal Transport Construction Investment Project Management Board, the city is simultaneously implementing seven projects, namely Tu Lien, Ngoc Hoi, Tran Hung Dao, Thuong Cat, Van Phuc, Hong Ha and Me So bridges. Construction is being carried out on multiple fronts, focusing on bored piles, pile caps, piers and superstructure works.

Dien Bien battlefield legacy powers tourism revival

Dien Bien battlefield legacy powers tourism revival

Seventy-two years after the Dien Bien Phu Victory, its legacy still reverberates. The unity, self-reliance, and resilience forged in that historic triumph remain a powerful internal engine, now propelling Dien Bien toward fast and sustainable development.

Hanoi accelerates shift to green buses, targets 100% by 2030

Hanoi accelerates shift to green buses, targets 100% by 2030

In the 2027–2030 period, the city will accelerate the transition towards the complete phase-out of fossil fuel-powered buses. The share of electric and green energy-fueled buses is projected to reach 79–89% by 2029 and 100% by 2030.

36 fishermen safely rescued after boat breaks down near Truong Sa

36 fishermen safely rescued after boat breaks down near Truong Sa

At 8:00 the same day, KN475 began towing the disabled fishing boat toward Da Tay A island. The towing operation was carried out safely, and by 18:30 both the vessel and its crew had arrived at the island without incident, where repairs and additional support procedures were arranged.

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Held in response to the launch of the Vietnamese Language Day among overseas Vietnamese communities, the event aimed to enhance the quality of Vietnamese language teaching and learning in Laos while contributing to the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between the two countries.

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Vietnamese language contest in Laos strengthens youth ties, bilateral friendship

Held in response to the launch of the Vietnamese Language Day among overseas Vietnamese communities, the event aimed to enhance the quality of Vietnamese language teaching and learning in Laos while contributing to the great friendship, special solidarity, comprehensive cooperation and strategic cohesion between the two countries.

Hanoi launches 10 electric bus routes from April 1

Hanoi launches 10 electric bus routes from April 1

By the end of April, the number of buses using electricity and other green energy sources in the city is expected to reach 822, including 683 electric buses and 139 compressed natural gas (CNG) buses, representing 42.1% of the total number of vehicles.